1. Home
  2. PMI
  3. PMI-RMP Exam

PMI-RMP PMI Risk Management Professional Exam Topics and Questions

Let's Practice Free PMI-RMP Questions Aligned with Official Exam Topics

Follows PMI's official outline Updated 08 Sep, 2026 5 Topics
Reviewed by Ava Lewis, PMI PMI-RMP Certified Professional
Topic Content

This topic anchors everything else. You'll spend the largest share of marks establishing how risk work will run, who owns what, and where the organisation's boundaries sit. The cost comes in two forms: missed document analysis that leaves you working blind, and misaligned thresholds that send responses in the wrong direction. – Document review and environmental assessment The preliminary document analysis pulls together industry benchmarks, lessons learned, historical data, and any other material that tells you what has already gone...

See More

The question below asks you to match a planning activity to a project stage, testing whether you can sequence risk work in context.

Sample Questions for Topic 1 : Risk Strategy and Planning
Q1

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Topic Content

Once strategy is set, you move into identification. This topic carries the highest weighting alongside Risk Analysis, and the cost is straightforward: risks you fail to identify cannot be managed. The work splits between running structured exercises and turning what you hear into a usable register. – Running identification exercises and analysing results You conduct meetings, interviews, focus groups, and other sessions with subject-matter experts, then perform detailed analysis of what comes back. That analysis covers documents, audio transcripts, telemetry...

See More

The question that follows tests whether you can distinguish a risk trigger from a risk cause in a project scenario.

Sample Questions for Topic 2 : Risk Identification
Q2

The project's customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?

Topic Content

Identification tells you what the risks are; analysis tells you what they mean. You carry the same 23 per cent weighting here, and the cost is misallocated effort: respond to the wrong risks and you burn budget without reducing exposure. – Qualitative analysis and prioritisation Qualitative analysis starts with nominal classification of risks in the Risk Breakdown Structure, using the categories from the risk management plan. You estimate the impact of each risk on schedule, budget, resources, and scope, then...

See More

The question below presents a risk profile and asks which analysis technique will yield the most useful result for the decision ahead.

Topic Content

Response is where analysis converts into action. The weighting drops to 13 per cent, but the cost of a wrong answer is immediate: an inappropriate response wastes budget, and a missed response lets the risk materialise. The work divides into planning the response and implementing it. – Planning and evaluating responses You determine the appropriate risk response strategy for each risk: avoid, accept, mitigate, enhance, or contingency planning. Response actions follow, time-bound and assigned to action owners. Effectiveness assessment comes...

See More

The question below describes a risk and asks which response strategy aligns with the stated project constraints and organisational appetite.

Topic Content

Monitoring closes the loop. At 19 per cent, this topic tests whether you can track what is happening, update what has changed, and communicate the current state. The cost is stale information: a risk register that no longer reflects reality cannot guide decisions. – Performance data and variance analysis You reconcile performance data and reports from risk-relevant work packages, then analyse the data to determine completion status against the baseline. Variance analysis follows, comparing actual performance to planned performance and...

See More

The question below gives you performance data and asks which monitoring action is appropriate given the variance and the stated thresholds.

Ready to Start Practicing?

Access all questions and start your exam preparation journey

Upgrade to Full PMI-RMP Exam Questions πŸš€
Exams Made Simple. Success Made Possible.