1. Home
  2. PMI
  3. PMI-SP Exam

PMI-SP PMI Scheduling Professional Exam Topics and Questions

Let's Practice Free PMI-SP Questions Aligned with Official Exam Topics

Follows PMI's official outline Updated 17 Sep, 2026 5 Topics
Reviewed by David Clark, PMI PMI-SP Certified Professional
Topic Content

Schedule Strategy sets the foundation for everything that follows. It's where you define how scheduling will work across the project lifecycle: what gets controlled, who approves changes, how baselines are managed, and which standards apply. The cost comes in the form of incomplete or inconsistent policy. If your configuration management procedures are vague or your schedule management plan leaves room for interpretation, you'll spend the rest of the project fighting ambiguity. – Configuration management and baseline control Task 1 addresses...

See More

The question below tests your ability to identify the correct configuration management control when baseline integrity is at risk.

Sample Questions for Topic 1 : Schedule Strategy
Q1

You are the project manager of the HGH Project. Thomas, your project sponsor, asked you to submit

status reports every week, but now he wants you to submit the status reports every other week.

What project management plan would you need to update to reflect this change

from Thomas?

Topic Content

Schedule Planning and Development is where strategy becomes a working model. At 31 percent, this is the heaviest topic on the exam, and that weight reflects the sheer number of decisions you make between initial scope decomposition and baseline approval. The cost is in the sequencing and resource logic. Get the dependencies wrong, miss a constraint, or underestimate durations, and the schedule becomes a fiction that no one trusts. – Decomposition and work definition Tasks 1 and 2 cover how...

See More

The question that follows focuses on selecting the correct action when resource constraints invalidate the initial schedule model.

Sample Questions for Topic 2 : Schedule Planning and Development
Q2

Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Management is fine with this, except after reviewing the template they had preferred Thomas to use 24-hour time periods for his project calendar rather than the 8-hour time periods as indicated. Thomas agrees, but now he has to update what document in his project management plan?

Topic Content

Schedule Monitoring and Controlling is the heaviest topic at 35 percent, and that tells you where the exam focus lies. This is not passive reporting. You're collecting status, auditing schedule logic, analyzing alternatives, incorporating approved changes, and maintaining baseline integrity, all while the project is moving. The cost is in the lag between when something goes wrong and when you detect it. Miss a status update cycle, skip an audit, or fail to recognize a critical path shift, and you're...

See More

The question below examines your ability to determine the correct response when a schedule audit reveals a logic error that affects the critical path.

Topic Content

Schedule Closeout accounts for 6 percent of the exam, but its weight understates its importance. Closeout is where you formalize acceptance, evaluate performance, capture lessons learned, and archive everything in a way that satisfies contractual requirements and supports future forensic analysis. The cost is in the incompleteness. If you skip the performance evaluation, fail to update organizational process assets, or archive files in a way that makes retrieval difficult, you lose the value of everything you learned during execution. How...

See More

The question that follows tests whether you can identify the missing step when final acceptance is delayed despite all deliverables being complete.

Topic Content

Stakeholder Communications Management closes the exam at 14 percent. This topic is not about reporting for its own sake; it's about maintaining stakeholder support and elevating awareness of issues that could derail the schedule. The cost is in the mismatch between what you communicate and what stakeholders need to hear. If your status updates are too detailed for senior management or too vague for the project team, or if you fail to communicate a schedule issue before it becomes a...

See More

The question below turns on your ability to select the correct communication action when a schedule issue threatens a contractual milestone.

Ready to Start Practicing?

Access all questions and start your exam preparation journey

Upgrade to Full PMI-SP Exam Questions πŸš€
Exams Made Simple. Success Made Possible.